Summary of Works Contracted by Polder by BWDB Division

From Blue Gold Program Wiki
Revision as of 11:13, 31 October 2021 by Guy.Jones (talk | contribs) (→‎Polder 2)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)

This page hosts a series of tables provide the quantity and amount of infrastructure works contracted for each polder by each of the six BWDB Division against the RDPP budget heads.

Presented contracted quantities and amounts are in BDT Lakh and as of March 2021.

Amounts are based on the following figures:

  • Work not yet awarded = vetted amount
  • Ongoing works = contract amount
  • Completed works = paid amount

Satkhira O&M-2[edit | edit source]

Polder 2[edit | edit source]

SI. No Work Items Quantity Amount
1 Re-sectioning of Embankment (km) 35.620 658.17
2 Retired Embankment (km) -   -  
3 Re-excavation of khals (km) 34.850 610.36
4 Repair of Regulator/Sluice with gate (nos.) 9 60.96
5 Repair of Inlets/Outlets  (nos.) -   -  
6 Construction of Drainage Regulator/ Sluice (nos.) 5 872.21
7 Construction Drainage Outlet  (nos.) -   -  
8 Construction of Irrigation Inlet (nos.) -   -  
9 Construction of culvert (nos.) 10 101.28
10 Pump shed (nos.) 4 37.73
11 Low cost Bank Protection work (km) LS 112.89
12 Rehabilitation of Interior Dike (km) -   -  
13 Closure/ Cross-bundh (km) -   -  
14 Supply of Drain pipe (m) 499 15.78
15 Flood damage repair / Breach Closing LS 30.04
16 GoB O&M LS 11.39
Total 2,654.04

Khulna O&M-1[edit | edit source]

Polder 25[edit | edit source]

SI. No Work Items Quantity Amount
1 Re-sectioning of Embankment (km) 6.4 132.23
2 Retired Embankment (km) - -
3 Re-excavation of khals (km) 50.84 913.75
4 Repair of Regulator/Sluice with gate (nos.) 10 123.94
5 Repair of Inlets/Outlets  (nos.) - -
6 Construction of Drainage Regulator/ Sluice (nos.) - -
7 Construction Drainage Outlet  (nos.) - -
8 Construction of Irrigation Inlet (nos.) - -
9 Construction of culvert (nos.) - -
10 Pump shed (nos.) - -
11 Low cost Bank Protection work (km) - 1.87
12 Rehabilitation of Interior Dike (km) - -
13 Closure/ Cross-bundh (km) - -
14 Supply of Drain pipe (m) 750 15.21
15 Flood damage repair / Breach Closing LS 62.05
16 GoB O&M - -
Total 1567.8

Polder 26[edit | edit source]

SI. No Work Items Quantity Amount
1 Re-sectioning of Embankment (km) 11.86 266.34
2 Retired Embankment (km) - -
3 Re-excavation of khals (km) 18.69 153.45
4 Repair of Regulator/Sluice with gate (nos.) 1 23.78
5 Repair of Inlets/Outlets  (nos.) - -
6 Construction of Drainage Regulator/ Sluice (nos.) 4 598.38
7 Construction Drainage Outlet  (nos.) - -
8 Construction of Irrigation Inlet (nos.) - -
9 Construction of culvert (nos.) 3 82.72
10 Pump shed (nos.) - -
11 Low cost Bank Protection work (km) - -
12 Rehabilitation of Interior Dike (km) - -
13 Closure/ Cross-bundh (km) - -
14 Supply of Drain pipe (m) 198 5.17
15 Flood damage repair / Breach Closing LS 4.98
16 GoB O&M LS 35.44
Total 1222.56

Polder 29[edit | edit source]

SI. No Work Items Quantity Amount
1 Re-sectioning of Embankment (km) 18.49 174.91
2 Retired Embankment (km) 1.47 272.7
3 Re-excavation of khals (km) 38.38 440.07
4 Repair of Regulator/Sluice with gate (nos.) 13 139.84
5 Repair of Inlets/Outlets  (nos.) - -
6 Construction of Drainage Regulator/ Sluice (nos.) 2 404.40
7 Construction Drainage Outlet  (nos.) - -
8 Construction of Irrigation Inlet (nos.) - -
9 Construction of culvert (nos.) - -
10 Pump shed (nos.) - -
11 Low cost Bank Protection work (km) LS 78.85
12 Rehabilitation of Interior Dike (km) - -
13 Closure/ Cross-bundh (km) - -
14 Supply of Drain pipe (m) 399.6 9.42
15 Flood damage repair / Breach Closing LS 47.40
16 GoB O&M LS 122.37
Total 1811.49

Polder 27/1[edit | edit source]

SI. No Work Items Quantity Amount
1 Re-sectioning of Embankment (km) - -
2 Retired Embankment (km) - -
3 Re-excavation of khals (km) 27.48 336.34
4 Repair of Regulator/Sluice with gate (nos.) 5 55.38
5 Repair of Inlets/Outlets  (nos.) - -
6 Construction of Drainage Regulator/ Sluice (nos.) - -
7 Construction Drainage Outlet  (nos.) - -
8 Construction of Irrigation Inlet (nos.) - -
9 Construction of culvert (nos.) - -
10 Pump shed (nos.) - -
11 Low cost Bank Protection work (km) - -
12 Rehabilitation of Interior Dike (km) 3.5 43.93
13 Closure/ Cross-bundh (km) - -
14 Supply of Drain pipe (m) 350 7.9
15 Flood damage repair / Breach Closing - -
16 GoB O&M - -
Total 614.4

Polder 27/2[edit | edit source]

SI. No Work Items Quantity Amount
1 Re-sectioning of Embankment (km) 2.7 52.5
2 Retired Embankment (km) - -
3 Re-excavation of khals (km) 5.74 75.96
4 Repair of Regulator/Sluice with gate (nos.) 3 20.02
5 Repair of Inlets/Outlets  (nos.) - -
6 Construction of Drainage Regulator/ Sluice (nos.) - -
7 Construction Drainage Outlet  (nos.) - -
8 Construction of Irrigation Inlet (nos.) - -
9 Construction of culvert (nos.) - -
10 Pump shed (nos.) - -
11 Low cost Bank Protection work (km) - -
12 Rehabilitation of Interior Dike (km) - -
13 Closure/ Cross-bundh (km) - -
14 Supply of Drain pipe (m) 100 2.59
15 Flood damage repair / Breach Closing - -
16 GoB O&M - -
Total 170.07

Polder 28/1[edit | edit source]

SI. No Work Items Quantity Amount
1 Re-sectioning of Embankment (km) - -
2 Retired Embankment (km) - -
3 Re-excavation of khals (km) 14.05 152.43
4 Repair of Regulator/Sluice with gate (nos.) 9 111.97
5 Repair of Inlets/Outlets  (nos.) - -
6 Construction of Drainage Regulator/ Sluice (nos.) - -
7 Construction Drainage Outlet  (nos.) - -
8 Construction of Irrigation Inlet (nos.) - -
9 Construction of culvert (nos.) - -
10 Pump shed (nos.) - -
11 Low cost Bank Protection work (km) - -
12 Rehabilitation of Interior Dike (km) 3.6 28.07
13 Closure/ Cross-bundh (km) - -
14 Supply of Drain pipe (m) 350 7.9
15 Flood damage repair / Breach Closing - -
16 GoB O&M - -
Total 468.26

Polder 28/2[edit | edit source]

SI. No Work Items Quantity Amount
1 Re-sectioning of Embankment (km) 0.15 9.00
2 Retired Embankment (km) - -
3 Re-excavation of khals (km) 24.80 549.78
4 Repair of Regulator/Sluice with gate (nos.) 6 127.78
5 Repair of Inlets/Outlets  (nos.) - -
6 Construction of Drainage Regulator/ Sluice (nos.) 1 287.26
7 Construction Drainage Outlet  (nos.) - -
8 Construction of Irrigation Inlet (nos.) - -
9 Construction of culvert (nos.) - -
10 Pump shed (nos.) - -
11 Low cost Bank Protection work (km) - 30.10
12 Rehabilitation of Interior Dike (km) - -
13 Closure/ Cross-bundh (km) - -
14 Supply of Drain pipe (m) 350 7.9
15 Flood damage repair / Breach Closing LS 11.09
16 GoB O&M LS 0.94
Total 1146.84

Khulna O&M-2[edit | edit source]

Polder 22[edit | edit source]

SI. No Work Items Quantity Amount
1 Re-sectioning of Embankment (km) 4.78 72.55
2 Retired Embankment (km) 0.55 19.73
3 Re-excavation of khals (km) 8.67 75.48
4 Repair of Regulator/Sluice with gate (nos.) 3 6.22
5 Repair of Inlets/Outlets  (nos.) 5 61.86
6 Construction of Drainage Regulator/ Sluice (nos.) - -
7 Construction Drainage Outlet  (nos.) 2 28.06
8 Construction of Irrigation Inlet (nos.) - -
9 Construction of culvert (nos.) - -
10 Pump shed (nos.) - -
11 Low cost Bank Protection work (km) LS 32.62
12 Rehabilitation of Interior Dike (km) 0.47 33.4
13 Closure/ Cross-bundh (km) - -
14 Supply of Drain pipe (m) 200 4.71
15 Flood damage repair / Breach Closing LS 60.51
16 GoB O&M LS 28.85
Total 407.53

Polder 30[edit | edit source]

SI. No Work Items Quantity Amount
1 Re-sectioning of Embankment (km) 15.98 110.94
2 Retired Embankment (km) - -
3 Re-excavation of khals (km) 25.35 355.29
4 Repair of Regulator/Sluice with gate (nos.) 14 98.34
5 Repair of Inlets/Outlets  (nos.) - -
6 Construction of Drainage Regulator/ Sluice (nos.) 1 418.22
7 Construction Drainage Outlet  (nos.) - -
8 Construction of Irrigation Inlet (nos.) - -
9 Construction of culvert (nos.) - -
10 Pump shed (nos.) - -
11 Low cost Bank Protection work (km) LS 70.72
12 Rehabilitation of Interior Dike (km) - -
13 Closure/ Cross-bundh (km) - -
14 Supply of Drain pipe (m) 400 9.43
15 Flood damage repair / Breach Closing LS 43.05
16 GoB O&M LS 19.95
Total 1210.96

Polder 31-part[edit | edit source]

SI. No Work Items Quantity Amount
1 Re-sectioning of Embankment (km) 15.49 377.26
2 Retired Embankment (km) 1.16 81.32
3 Re-excavation of khals (km) 29.74 321.73
4 Repair of Regulator/Sluice with gate (nos.) 5 75.39
5 Repair of Inlets/Outlets  (nos.) - -
6 Construction of Drainage Regulator/ Sluice (nos.) 2 434.10
7 Construction Drainage Outlet  (nos.)
8 Construction of Irrigation Inlet (nos.) 1 26.53
9 Construction of culvert (nos.) - -
10 Pump shed (nos.) - -
11 Low cost Bank Protection work (km) - -
12 Rehabilitation of Interior Dike (km) - -
13 Closure/ Cross-bundh (km) - -
14 Supply of Drain pipe (m) 200 4.72
15 Flood damage repair / Breach Closing LS 8.14
16 GoB O&M LS 19.33
Total 1428.39

Polder 34/2-part[edit | edit source]

SI. No Work Items Quantity Amount
1 Re-sectioning of Embankment (km) 14.79 258.07
2 Retired Embankment (km) 2.18 75.46
3 Re-excavation of khals (km) 24.95 321.37
4 Repair of Regulator/Sluice with gate (nos.)
5 Repair of Inlets/Outlets  (nos.) - -
6 Construction of Drainage Regulator/ Sluice (nos.) 3 559.48
7 Construction Drainage Outlet  (nos.) - -
8 Construction of Irrigation Inlet (nos.) - -
9 Construction of culvert (nos.) - -
10 Pump shed (nos.) - -
11 Low cost Bank Protection work (km) - -
12 Rehabilitation of Interior Dike (km) 5.19 91.28
13 Closure/ Cross-bundh (km) - -
14 Supply of Drain pipe (m) 200 4.71
15 Flood damage repair / Breach Closing LS 89.76
16 GoB O&M LS 77.29
Total 1628.4

Patuakhali O&M[edit | edit source]

Polder 43/2A[edit | edit source]

SI. No Work Items Quantity Amount
1 Re-sectioning of Embankment (km) 29.65 371.50
2 Retired Embankment (km) 3.71 263.61
3 Re-excavation of khals (km) 26.19 255.78
4 Repair of Regulator/Sluice with gate (nos.) 4 57.17
5 Repair of Inlets/Outlets  (nos.) 36 33.36
6 Construction of Drainage Regulator/ Sluice (nos.) 3 509.00
7 Construction Drainage Outlet  (nos.) 4 382.37
8 Construction of Irrigation Inlet (nos.)
9 Construction of culvert (nos.) - -
10 Pump shed (nos.) - -
11 Low cost Bank Protection work (km) LS 2.76
12 Rehabilitation of Interior Dike (km) - -
13 Closure/ Cross-bundh (km) - -
14 Supply of Drain pipe (m) 556.32 15.69
15 Flood damage repair / Breach Closing LS 29.24
16 GoB O&M LS 35.38
Total 2062.86

Polder 43/2B[edit | edit source]

SI. No Work Items Quantity Amount
1 Re-sectioning of Embankment (km) 16.47 172.85
2 Retired Embankment (km) 1.4 65.33
3 Re-excavation of khals (km) 41.06 588.01
4 Repair of Regulator/Sluice with gate (nos.) 5 71.63
5 Repair of Inlets/Outlets  (nos.) 42 22.98
6 Construction of Drainage Regulator/ Sluice (nos.) 2 793.52
7 Construction Drainage Outlet  (nos.) 2 148.48
8 Construction of Irrigation Inlet (nos.)
9 Construction of culvert (nos.) - -
10 Pump shed (nos.) - -
11 Low cost Bank Protection work (km) - -
12 Rehabilitation of Interior Dike (km) 2.22 26.37
13 Closure/ Cross-bundh (km) LS 20.58
14 Supply of Drain pipe (m) 556.32 15.69
15 Flood damage repair / Breach Closing LS 56.25
16 GoB O&M LS 34.09
Total 2170.81

Polder 43/2D[edit | edit source]

SI. No Work Items Quantity Amount
1 Re-sectioning of Embankment (km) 32.8 210.18
2 Retired Embankment (km) - -
3 Re-excavation of khals (km) 43.93 553.77
4 Repair of Regulator/Sluice with gate (nos.) 17 160.21
5 Repair of Inlets/Outlets  (nos.) 49 55.00
6 Construction of Drainage Regulator/ Sluice (nos.) 1 234.22
7 Construction Drainage Outlet  (nos.) 2 175.25
8 Construction of Irrigation Inlet (nos.)
9 Construction of culvert (nos.) - -
10 Pump shed (nos.) - -
11 Low cost Bank Protection work (km) - -
12 Rehabilitation of Interior Dike (km) - -
13 Closure/ Cross-bundh (km) - -
14 Supply of Drain pipe (m) 556.32 15.73
15 Flood damage repair / Breach Closing LS 6.45
16 GoB O&M LS 0.87
Total 1520.21

Polder 43/2E[edit | edit source]

SI. No Work Items Quantity Amount
1 Re-sectioning of Embankment (km) 3.03 34.70
2 Retired Embankment (km) - -
3 Re-excavation of khals (km) 4.60 18.13
4 Repair of Regulator/Sluice with gate (nos.) 7 40.89
5 Repair of Inlets/Outlets  (nos.) 42 19.70
6 Construction of Drainage Regulator/ Sluice (nos.) - -
7 Construction Drainage Outlet  (nos.) - -
8 Construction of Irrigation Inlet (nos.) - -
9 Construction of culvert (nos.) - -
10 Pump shed (nos.) - -
11 Low cost Bank Protection work (km) - -
12 Rehabilitation of Interior Dike (km) - -
13 Closure/ Cross-bundh (km) - -
14 Supply of Drain pipe (m) 201.3 5.69
15 Flood damage repair / Breach Closing - -
16 GoB O&M - -
Total 156.73

Polder 55/2A[edit | edit source]

SI. No Work Items Quantity Amount
1 Re-sectioning of Embankment (km) 15.06 135.62
2 Retired Embankment (km) - -
3 Re-excavation of khals (km) 17.93 227.73
4 Repair of Regulator/Sluice with gate (nos.) 12 255.45
5 Repair of Inlets/Outlets  (nos.) - -
6 Construction of Drainage Regulator/ Sluice (nos.) 1 514.14
7 Construction Drainage Outlet  (nos.) 1 111.45
8 Construction of Irrigation Inlet (nos.)
9 Construction of culvert (nos.) - -
10 Pump shed (nos.) - -
11 Low cost Bank Protection work (km) - -
12 Rehabilitation of Interior Dike (km) 6 119.97
13 Closure/ Cross-bundh (km) - -
14 Supply of Drain pipe (m) 556.32 15.73
15 Flood damage repair / Breach Closing LS 6.54
16 GoB O&M LS 38.47
Total 1592.78

Polder 55/2C[edit | edit source]

SI. No Work Items Quantity Amount
1 Re-sectioning of Embankment (km) 17.76 154.17
2 Retired Embankment (km) 4.66 85.28
3 Re-excavation of khals (km) 19.4 208.81
4 Repair of Regulator/Sluice with gate (nos.) 7 147.03
5 Repair of Inlets/Outlets  (nos.) - -
6 Construction of Drainage Regulator/ Sluice (nos.) 1 235.68
7 Construction Drainage Outlet  (nos.) 1 138.34
8 Construction of Irrigation Inlet (nos.)
9 Construction of culvert (nos.) - -
10 Pump shed (nos.) - -
11 Low cost Bank Protection work (km) - -
12 Rehabilitation of Interior Dike (km) - -
13 Closure/ Cross-bundh (km) - -
14 Supply of Drain pipe (m) 556.32 15.72
15 Flood damage repair / Breach Closing LS 76.23
16 GoB O&M LS 13.07
Total 1249.31

Barguna O&M[edit | edit source]

Polder 43/1A[edit | edit source]

SI. No Work Items Quantity Amount
1 Re-sectioning of Embankment (km) 18.42 216.79
2 Retired Embankment (km) - -
3 Re-excavation of khals (km) 15.88 166.61
4 Repair of Regulator/Sluice with gate (nos.) 5 32.22
5 Repair of Inlets/Outlets  (nos.) 16 13.95
6 Construction of Drainage Regulator/ Sluice (nos.) - -
7 Construction Drainage Outlet  (nos.) - -
8 Construction of Irrigation Inlet (nos.) - -
9 Construction of culvert (nos.) - -
10 Pump shed (nos.) - -
11 Low cost Bank Protection work (km) - -
12 Rehabilitation of Interior Dike (km) - -
13 Closure/ Cross-bundh (km) - -
14 Supply of Drain pipe (m) 500 11.6
15 Flood damage repair / Breach Closing - -
16 GoB O&M - -
Total 504.37

Polder 43/2F[edit | edit source]

SI. No Work Items Quantity Amount
1 Re-sectioning of Embankment (km) 33.00 199.27
2 Retired Embankment (km) - -
3 Re-excavation of khals (km) 22.31 275.16
4 Repair of Regulator/Sluice with gate (nos.) 16 94.07
5 Repair of Inlets/Outlets  (nos.) 41 65.68
6 Construction of Drainage Regulator/ Sluice (nos.) 2 418.57
7 Construction Drainage Outlet  (nos.) 4 209.39
8 Construction of Irrigation Inlet (nos.)
9 Construction of culvert (nos.) - -
10 Pump shed (nos.) - -
11 Low cost Bank Protection work (km) - -
12 Rehabilitation of Interior Dike (km) - -
13 Closure/ Cross-bundh (km) - -
14 Supply of Drain pipe (m) 500 11.60
15 Flood damage repair / Breach Closing LS 43.61
16 GoB O&M - -
Total 1425.87

Kalapara[edit | edit source]

Polder 47/3[edit | edit source]

SI. No Work Items Quantity Amount
1 Re-sectioning of Embankment (km) 14.86 191.03
2 Retired Embankment (km) - -
3 Re-excavation of khals (km) 12.57 207.64
4 Repair of Regulator/Sluice with gate (nos.) 8 182.26
5 Repair of Inlets/Outlets  (nos.) 3 1.61
6 Construction of Drainage Regulator/ Sluice (nos.) 1 250.47
7 Construction Drainage Outlet  (nos.) - -
8 Construction of Irrigation Inlet (nos.) - -
9 Construction of culvert (nos.) - -
10 Pump shed (nos.) - -
11 Low cost Bank Protection work (km) - -
12 Rehabilitation of Interior Dike (km) - -
13 Closure/ Cross-bundh (km) - -
14 Supply of Drain pipe (m) 500 14.88
15 Flood damage repair / Breach Closing - -
16 GoB O&M LS 14.29
Total 969

Polder 47/4[edit | edit source]

SI. No Work Items Quantity Amount
1 Re-sectioning of Embankment (km) 22.85 393.74
2 Retired Embankment (km) 5.45 210.85
3 Re-excavation of khals (km) 37.6 690.10
4 Repair of Regulator/Sluice with gate (nos.) 23 651.84
5 Repair of Inlets/Outlets  (nos.) 1 3.00
6 Construction of Drainage Regulator/ Sluice (nos.) 2 481.52
7 Construction Drainage Outlet  (nos.) 3 271.58
8 Construction of Irrigation Inlet (nos.)
9 Construction of culvert (nos.) - -
10 Pump shed (nos.) - -
11 Low cost Bank Protection work (km) LS 55.72
12 Rehabilitation of Interior Dike (km) 27.15
13 Closure/ Cross-bundh (km) - -
14 Supply of Drain pipe (m) 500 14.88
15 Flood damage repair / Breach Closing LS 172.57
16 GoB O&M LS 69.94
Total 3403.82